Hollystown Park GAA Cluster Facility
Live
The Dublin County Board G.A.A. is developing a GAA cluster facility which will include, in summary; 4 No. floodlit pitches, the alteration/refurbishment of the existing clubhouse and the construction of a two storey extension thereto, a warm up area, indoor training pitch, hurling wall, a spectator stand for up to 500 people, hurling wall, with car parking, coach and bicycle parking facilities on the lands of the former Hollystown Golf Club in Co. Dublin. Total development size 9.3Ha of which 6.2Ha is pitches and 3,240m2 is new /refurbished buildings.
A description of the GAA Cluster Facility at Hollystown is listed below.
Playing Pitches and External Works
The external works consist of the following elements;
- 3 Full size (145m x 90m) sand-based grass, drained playing pitches (Pitches No. 1, 3 and 4) with 5m run-off area, of which Pitch No. 1 will be primary pitch for competitions, being located close to the buildings with spectator seating alongside. These pitches will have an engineered drainage system consisting of slit drains, feeding into pitch drains and from there to collector drains, this approach ensures a better playing surface with greater pitch endurance.
- 1 Full size (145m x 90m) all weather artificial grass (3G with shock pad), drained playing pitch (Pitch No. 2) with 5m run-off area. The all-weather pitch will be fenced off to protect it against unauthorized usage, thus preserving the playing surface.
- 2 no. dugouts and scoreboard to all pitches.
- Floodlighting to all four pitches (350 lux for Pitches No’s 2, 3 and 4, with primary pitch; Pitch No.1, lit to 500 lux). Typical 6 columns per pitch, with the exception of Pitch No. 1, which has 7 no, all with 21.3m high.
- Two sets of goals (12m high goalposts, 6.5m wide crossbar and nets) for each pitch.
- Ball-stop netting (12m high x 30m long) to the rear of each goal.
- Railing around each of Pitches No. 1, 3 and 4.
- Warm up/Shuttle Run areas.
- Walking/Jogging trail (c.1km long x 3.7m wide) around the full perimeter of the site with outdoor exercise equipment accessible to the public. Note this trail facilitates emergency access to the playing pitches.
- Car parking (63 spaces of which 9 are universal access and 4 electrical charging) and Coach parking (4 Spaces) on existing hard standing to the front, and new permeable paving to the side and rear of the pavilion.
- 50 Bicycle Stands which can accommodate parking of 100 bicycles and 2 electric bicycle charging points.
- New Entrance for vehicles, cyclists and pedestrians to be constructed onto the Kilbride Road.
- Overflow car parking, as required (up to 100 additional spaces) on grasscrete or similar porous surface.
- Planting/Landscaping around perimeter.
- 3 No. Pedestrian / Cycle Access Gates along southern boundary to adjacent landscaped corridor
- Earthworks and minor retaining structures.
- Entrance sign for development.
Buildings & Structures;
- Upgrade to existing clubhouse (existing area 678m2) with the provision of 4 team changing rooms (2 existing and 2 new, through alteration of existing bar layout, typically 62m2 each and with new external access door), officials changing room, showers and toilets on the ground floor, retention of existing kitchen facilities, re-purposing of first floor to offices and team meeting space/multi-purpose room, including removal of external stairs.
- Construction of new two-storey extension (area 1,276m2) 10.06m high to provide 6 team changing rooms (59m2 each), showers and toilets, baths and physio rooms, plant room and toilets for spectators, all on ground floor. New 300m2 Gymnasium, storerooms, office and physio space and team meeting space/multi-purpose room on first floor. New access stairs and lift as well as terrace and green roof and photovoltaic solar panels.
- Separate Indoor Training Facility (area 820m2) 7.25m high with 30m x 20m pitch, team tactics space, toilets, plant room and store for equipment.
- Spectator Stand (area 296m2) 7m high to accommodate 500 spectators with partial roof/cover, and undercroft equipment store on eastern side of Pitch No.1.
- Hurling walls (9m x 9.5m) 5m high and fenced in, floodlit astro-turf hurling practice area.
- ESB Substation (area 42m2) and switch room.
- A maintenance & equipment building (area 128m2) 4.3m high.
- Demolition of existing driving range and pro-shop shed (existing area 72m2).